October 21, 2022 | By CCG Residential Construction | Project Update

The Edge at Middleton located in Aberdeen, MD has seen notable changes. Building A's MEP rough-ins are substantially complete and the roof is near completion. Building B & C's framing are largely done and Building C's MEP has started. Along with the buildings, the site grading is heavily complete, and site topsoil spreading is ongoing.

The Edge at Middleton located in Aberdeen, MD has seen notable changes. Building A's MEP rough-ins are substantially complete and the roof is near completion. Building B & C's framing are primarily done and Building C's MEP has started. Along with the buildings, the site grading is heavily complete, and site topsoil spreading is ongoing.

In the next 30 days, layout and excavation of the pool will take place and Building B's installation of windows will begin. For Building C and the Commons Building the roofing will start. As for Building A, fabrication of handrails and guardrails will take place along with the completion of stairs.

Check back later for more updates on this large Multi-Family project coming to Aberdeen, MD in the Fall of 2023.

Recent News

Project Update: Eagle Park Vistas and Villages
CCG Residential Construction is making substantial progress of Eagle Park Vistas and Villages. Located in Hanover, MD and...
Recently Awarded: Waldorf Technology Park Apartments
CCG Residential Construction has recently been awarded Waldorf Technology Park Apartments located in Waldorf, MD...
Company News: Aura Topping Out
Last Friday, Chesapeake celebrated the topping out of the Aura, a CCG Residential project located in Largo, MD...