October 21, 2022 | By CCG Residential Construction | Project Update

The Edge at Middleton located in Aberdeen, MD has seen notable changes. Building A's MEP rough-ins are substantially complete and the roof is near completion. Building B & C's framing are largely done and Building C's MEP has started. Along with the buildings, the site grading is heavily complete, and site topsoil spreading is ongoing.

The Edge at Middleton located in Aberdeen, MD has seen notable changes. Building A's MEP rough-ins are substantially complete and the roof is near completion. Building B & C's framing are primarily done and Building C's MEP has started. Along with the buildings, the site grading is heavily complete, and site topsoil spreading is ongoing.

In the next 30 days, layout and excavation of the pool will take place and Building B's installation of windows will begin. For Building C and the Commons Building the roofing will start. As for Building A, fabrication of handrails and guardrails will take place along with the completion of stairs.

Check back later for more updates on this large Multi-Family project coming to Aberdeen, MD in the Fall of 2023.

Recent News

Project Update: 501 Hillsborough
CCG Residential Construction was selected for a mixed-use project located at 501 Hillsborough in Raleigh, North Carolina...
Company News: CCGR Team heads to NMHC
Ronnie Brouillard and Daniel Hannon are headed to the National Multifamily Housing Council Annual Meeting next week...
Project Update: The Residences at Sandy Farms
Located in Severn, MD, The Residences at Sandy Farms is a 414,000 SF, 4 story, wood framed multifamily project designed by Poole...
Safety: The Residence at Sandy Farms Safety Orientation
Here at CCG Residential, safety is the concrete foundation that sits at the core of our work. All of our jobsites follow...