Woodyard Station
![](https://www.ccgres.com/wp-content/uploads/fly-images/4401/Chesapeake-Contracting-Group-Woodyard-Clinton-Maryland-Camera-September_01_2022_12_03_00_PM-1-968x511-c.jpg)
Great progress happening at Woodyard Station. The two 4-story buildings have been framed and windows and roofs installed.
Currently, the multi-family and senior building are having brick veneer and Hardie siding put in place and mechanical, electrical, and plumbing rough in is underway. The multi-family building is also being insulated while the senior building is being pre-rocked.
Next on the schedule is asphalt paving of the parking lot and installing drywall in the multi-family building.
Check back later to see more updates on this 158-unit residential project coming to Clinton, Maryland.
Recent News
![](https://www.ccgres.com/wp-content/uploads/fly-images/4686/42920B3B-A00E-4612-8ADD-ADB41D280FA5-scaled-314x225-c.jpeg)
Project Update: Aura
Aura is making exciting progress! Once complete, this 6-story, 570,639 SF apartment building for Klein Enterprises and The...